Niraj Cement Structurals Limited has successfully secured two significant work orders from the Northeast Frontier Railway (NF Railway), marking a substantial expansion of its domestic infrastructure portfolio.
These domestic contracts, collectively valued at approximately ₹230.06 Crores, underscore the company’s growing presence in the national railway sector.
The first contract involves the construction of both the substructure and superstructure for Bridge No. 312/A. This project, a Road Over Bridge (ROB) located between the Bilasipara and Chapar stations, is part of the New Maynaguri-Jogighopa New B.G. Line Project.
Valued at ₹50.95 Crores (inclusive of GST), this specific assignment is scheduled for completion within a 12-month timeframe.
Simultaneously, the company has been awarded a larger mandate valued at ₹179.11 Crores. This project encompasses the construction of nine minor bridges, the completion of wing and return walls for various major bridges, and the installation of height gauges in several Road Under Bridges (RUBs).
These works are situated within the Araria-Galgalia Project and the RNI-BPMS siding, with an accelerated execution period of 9 months.
Neither project involves any interest from the company’s promoters or group entities, and they are not classified as related party transactions.
This double-win highlights Niraj Cement Structurals’ capacity to handle diverse and time-sensitive railway infrastructure projects across India.
This disclosure was signed by Anil Anant Jha, Company Secretary & Compliance Officer. The notification was made pursuant to Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.
Disclaimer: The information provided is for educational purposes only and does not constitute financial advice. We are not registered financial advisors. Please conduct your own research and consult a qualified advisor before making investment decisions. Any investment decisions you make based on this information are solely at your own risk.